White paper 01 · Chapter 11

Next studies: what comes next and how it will be established

The conclusions of this paper rest on public evidence that is strong on ore reserves, trade flows, prices and policy. Five subjects lead the next studies: DR-grade feed from Cameroonian ore at industrial scale, the gas available for industry at Kribi, the cost of heavy-industry power and the allocation of the shared supply at the port, the terms of supply under the 15% rule, and the contracts for the first phase’s imported iron units. This chapter lists the studies, explains why each matters and sets out its method, its lead and its timing.

Reading
8 min
Length
1,768 words
Edition of
10 October 2026
In this chapter (3)
  1. 11.1 Why a register of next studies matters
  2. 11.2 The five studies that matter most
  3. 11.3 How these studies will be carried out

11.1 Why a register of next studies matters

A public white paper earns its credibility one number at a time. Throughout this paper, figures that could not be traced to a published source or to Cameroon Steel’s reference configuration were left out, and figures that rest on company statements, snippets or dated studies were labelled as such. The next questions call for tests, surveys and data beyond today’s public sources. Most of them concern the later phases; five (E6, E8, E10, E11 and E18) are scheduled before Phase 1. Table 11.1 sets them out, with the party best placed to lead each study and a target date.

Table 11.1 Register of next studies: subject, importance, method, lead and timing

# Study Why it matters Method Who When (target) Needed before
E1 DR-grade concentrate from Mbalam itabirite or Lobé magnetite at industrial scale, building on the 2014 testwork [O04] Decides whether the DR module can use Cameroonian ore Pilot-scale grinding, flotation or magnetic separation, pelletising and reduction tests; independent laboratory Convention holders with Cameroon Steel; independent laboratory 2027 to 2030 DR module
E2 A certified resource and mine plan for the ore dedicated to local supply Gives the DR module a code-compliant feed base JORC or NI 43-101 statement for the relevant itabirite or magnetite blocks Convention holders; Ministry of Mines 2028 to 2032 DR module
E3 The DR-grade pellet premium and delivered pellet prices, which are negotiated in private contracts [N16] Sets the cost of imported pellets and the value of local concentrate Indicative offers from pellet producers; subscription price data Cameroon Steel At each feasibility update DR module
E4 Remaining certified gas reserves at Sanaga Sud and their decline profile [E02] Sizes the supply of a 1 Mtpa DR module for its life Independent reserve audit; SNH and operator data SNH; Ministry of Mines; field operator 2026 to 2028 DR module
E5 Whether the tax on natural gas applies to gas used as a reductant [E11] Changes the gas cost per tonne of DRI Ruling from the tax administration Tax administration 2027 DR module
E6 Power tariff and terms for loads above 10 MW at Kribi [E15]; the steelworks’ allocation within the first 100 MW, which serves the whole port platform; power-quality measures for the arc furnace (static VAR compensation, short-circuit capacity) Determines the operating cost and the connection of every phase Published framework or negotiated term sheet; allocation set with the grid operator; connection study Ministry of Water and Energy; regulator; grid operator; Cameroon Steel 2027 to 2028, during front-end engineering Phase 1
E7 Timing of the later 330 to 400 MW stage of the Kribi substation [Z43] Paces the full chain and the DR module Utility and port investment plan Ministry of Water and Energy; grid operator; port authority 2028 to 2030 Phases 2 and 3
E8 Current national scrap arising, updating the 2006 study [C42]; RC-1.1 assumes about 30 kt/yr for the works (0 to 60) [F01] Sizes the domestic share of the melt-shop charge New survey of arising, collection and prices Ministry of Mines; industry body 2027 Phase 1
E9 Cameroon’s import detail for 2024 and 2025 by six-digit HS line, ahead of its UN Comtrade release [C06] Updates the billet, section and flat-product import figures Customs data from the DGD or INS Customs (DGD); INS 2027 Phases 2 and 3
E10 Douala and Yaoundé steel prices for 2024 to 2026, and the current homologated list [C44] Updates the domestic price premium and margin estimates Ministry of Commerce lists; market survey Ministry of Commerce 2027 Phase 1
E11 Steel-line rates in the new CEEAC-CEMAC tariff [P23]; AfCFTA rules of origin for chapter 72 [P31] Decides protection levels and export eligibility Customs notices; AfCFTA e-tariff book Customs; CEMAC; AfCFTA Secretariat 2026 to 2027 Phase 1
E12 Terms of the 15% clauses in the Mbalam and Lobé conventions [O17][O33] Decides grade, price and timing of local supply Publication of terms; implementing text for art. 40(4) Ministry of Mines; convention holders 2027, with the implementing text DR module
E13 Start date of Mbalam exports, scheduled for 2027, and of its rail phase from 2030 [O28][O25] Sets the earliest date for local ore at scale Company and ministry reporting Mbalam convention holder; Ministry of Mines Continuous reporting DR module
E14 Status of Bipindi-Grand Zambi exports after mid-2025 [O38] A possible early source of concentrate near Kribi Company and port reporting Project holder; port authority Continuous reporting DR module
E15 Capacity and timing of the Kribi mineral terminal: MoU of 4 November 2025, completion expected within five to six years of March 2026 [O31][Z4] Bulk handling for pellets, concentrate and HBI Project structuring documents Port authority; terminal consortium 2026 to 2027 (structuring) DR module
E16 Capital costs for DR modules, pellet plants and section mills in Africa Sets the investment plan of each phase; not stated in this public paper Supplier quotations; feasibility studies Cameroon Steel; suppliers At each feasibility study Each phase
E17 Final 2026 census population [C14] Changes per-capita steel use by up to a third INS publication of final results INS 2027 Context only
E18 Supply contracts and delivered cost of imported HBI or DRI and scrap for Phase 1, in a world market where about 10.8 Mt of DRI was traded in 2025 [T13] Sets the cost and security of Phase 1’s charge, which is mostly imported Indicative offers and supply agreements with several origins; delivered-cost model to Kribi Cameroon Steel 2027 to 2028, during front-end engineering Phase 1

Source: Cameroon Steel. Sources in square brackets point to the latest public evidence on each question. Target dates are Cameroon Steel’s planning targets, tied to the RC-1.1 schedule; dates for public bodies are proposals, not their commitments.

11.2 The five studies that matter most

Grade (E1, E2). Local ironmaking rests on upgrading Cameroonian ore economically to about 67.5% Fe with low silica and alumina. The 2014 testwork result of 68% Fe with 1.8% silica and 0.2% alumina [O04] is encouraging; it was obtained in the laboratory on a limited sample, which the pilot programme will extend. That programme will test representative samples from the blocks that would supply local transformation, through every step from grinding to reduction. Its results will decide whether the conventional gas-DRI route is open, or whether the smelter route described in Chapter 2 is the better option.

Gas (E4, E5). The departure of the LNG vessel in July 2026 [E09] makes gas available for industry. The reserves behind it are to be certified, and about 600 bcf were developed for the vessel and are in natural decline [E02]. A DR module of 1 Mtpa would need 8.4 to 9.1 bcf a year for perhaps twenty years or more. An independent reserve audit, the study that sizes that supply for the module’s life, comes before the DR module.

Power (E6, E7). The first phase is designed within the initial 100 MW of the Kribi supply, which serves the whole port platform; the steelworks’ allocation and the power-quality measures at the connection are the first items of this study. Its operating cost will be set by a high-voltage contract under the framework recommended in Chapter 10 (G6), and the later phases follow the timing of the 330 to 400 MW stage of the substation.

Offtake terms (E12). The 15% rule is the legal hook for local ironmaking. The terms of the clauses in the existing conventions, together with the implementing text recommended in Chapter 10 (G1), will set grade, price and timing, and with them the full value of the rule to a local processor.

Iron units for Phase 1 (E8, E18). The first phase runs on iron units traded worldwide rather than on Cameroonian ore. RC-1.1 assumes about 30 kt/yr of domestic scrap, within a range of 0 to 60 kt/yr bounded by the 2006 national study [C42][F01]; the rest of a charge of about 0.36 Mtpa is imported as scrap, DRI or HBI, in a world market where about 10.8 Mt of DRI was traded in 2025 [T13]. Supply agreements with several origins and a delivered-cost model to Kribi are scheduled during front-end engineering, ahead of the first heat.

11.3 How these studies will be carried out

Cameroon Steel will carry out the studies within its remit as part of the feasibility work for each phase and will publish what it can in later editions of this series. Several studies lie with public bodies and convention holders: the gas audit, the power framework, the tariff lines, the rules of origin and the publication of convention terms. Chapter 10 recommends that the Prime Minister’s mines-metallurgy committee coordinate them, because they cut across ministries and companies.

Three principles will govern updates of this paper:

  1. Every new figure will carry its source and date, and figures that change will be shown with their previous value.
  2. Company and official statements will remain labelled as such until they are supported by code-compliant estimates or published data.
  3. Project figures will remain labelled planned or indicative until they are fixed by detailed engineering. The project’s financing is approved and available.

Sources cited in this chapter

Bracketed markers refer to these sources; the full list is in the annex. Full list of sources

  1. O04Mbalam-Nabeba project presentation, Mining Indaba 2014 (itabirite testwork). Former holder of the Mbalam-Nabeba project (ASX-listed), Feb 2014.sdl.live.irmau.com/irm/PDF/2752_0/PresentationMiningIndaba2014
  2. N16Launch of DR-grade iron ore pellet premium weekly indicator. Fastmarkets, 1 Dec 2022.fastmarkets.com/insights/launch-of-dr-grade-iron-ore-pellet-premium-we…
  3. E02Cameroon’s SNH eyes Yoyo-Yolanda and new exploration blocks to sustain gas growth. Business in Cameroon, 6 Jul 2026.businessincameroon.com/energy/0607-16422-cameroon-s-snh-eyes-yoyo-yola…
  4. E11Industrial gas: Cameroon suspends GDC’s 20% price hiking plan. Business in Cameroon, 18 Jul 2023.businessincameroon.com/energy/1807-13291-industrial-gas-cameroon-suspe…
  5. E15Rapport d’activités 2025 de l’ARSEL. ARSEL (electricity regulator), 7 Sep 2026.arsel-cm.org/wp-content/uploads/2026/09/Rapport-ARSEL-2025.pdf
  6. Z43Kribi franchit la ligne électrique 225 kV. PAK, 6 Aug 2025.Cited by title and date
  7. C42Bidoung J., Fomethe A., Yantio G., Melo U., La récupération et le recyclage des déchets ferromagnétiques: analyse de la situation au Cameroun (Déchets, Revue francophone d’écologie industrielle n°48). ENSP Yaoundé / MIPROMALO, Q4 2007.eid.episciences.org/7942/pdf
  8. F01Cameroon Steel reference configuration RC-1 (planning estimate), edition 10 October 2026 (RC-1.1). Cameroon Steel, 10 Oct 2026.Cited by title and date
  9. C06UN Comtrade public API, Cameroon (reporter 120), HS 72/73 and 6-digit lines, 2019-2023. UN Statistics Division.comtradeapi.un.org/public/v1/preview/C/A/HS?reporterCode=120&period=20…
  10. C44Fer à béton: les producteurs acceptent une baisse des prix. EcoMatin, 23 Oct 2023.ecomatin.net/fer-a-beton-les-producteurs-acceptent-une-baisse-des-prix
  11. P23Cameroon applies CEEAC common external tariff from January 1, 2026. Business in Cameroon, 12 Jan 2026.businessincameroon.com/public-management/1201-15594-cameroon-applies-c…
  12. P31AfCFTA e-Tariff Book. AfCFTA Secretariat, n.d..au-afcfta.org/etariff/
  13. O17Cameroon Mining Company confirme l’entrée du projet Mbalam dans sa phase irréversible d’exécution. Camer.be via AllAfrica, 12 Dec 2025.fr.allafrica.com/stories/202512120475.html
  14. O33Fer de Lobé: l’État octroie le permis d’exploitation à Sinosteel. EcoMatin, 7 Sep 2022.ecomatin.net/fer-de-lobe-malgre-des-contestations-letat-octroie-le-per…
  15. O28Exploitations: la revue des gisements. Cameroon Tribune, 11 May 2026.cameroon-tribune.cm/articles/11125/fr/details_2
  16. O25Mbalam iron ore mine delays first exports to early 2026. Business in Cameroon, 13 Dec 2025.businessincameroon.com/public-management/1312-15495-mbalam-iron-ore-mi…
  17. O38Grand Zambi iron ore project now targets first exports in August 2025. Business in Cameroon, 3 Jun 2025.businessincameroon.com/mining/0306-14716-grand-zambi-iron-ore-project-…
  18. O31CNPS, G-Stones join Kribi port mineral terminal project. Business in Cameroon, 7 Nov 2025.businessincameroon.com/mining/0711-15312-cnps-g-stones-join-kribi-port…
  19. Z4Zone industrialo-portuaire de Kribi (KPIZ): jusqu’à +8 points de croissance et 150 000 emplois…. Investir au Cameroun, 4 Mar 2026.investiraucameroun.com/gestion-publique/0403-23163-zone-industrialo-po…
  20. C14Cameroun: bouclage du 4e RGPH, 22,7 millions d’habitants recensés. Journal du Cameroun, 5 Oct 2026.fr.journalducameroun.com/cameroun-bouclage-du-4e-rgph-227-millions-dha…
  21. T132025 World Direct Reduction Statistics. Midrex Technologies, Sep 2026.midrex.com/world-dri-statistics/world-dri-production-reaches-151-0-mt-…
  22. E09Le navire usine quitte le Cameroun, le gaz s’arrête. Camer.be, 9 Jul 2026.camer.be/93911/12:1/le-navire-usine-quitte-le-cameroun-le-gaz-sarrete-…

Cite this chapter

Cameroon Steel (2026). From ore to steel: Cameroon’s missing link is ironmaking, not rolling. White paper 01, chapter 11: Next studies: what comes next and how it will be established. CS-WP-01. https://www.cameroon-steel.com/en/library/ore-to-steel/evidence-gaps/