Is the plant already operating?
No. The project is in development. The foundation stone was laid on 30 December 2024. The project’s financing is approved and available. The next steps are front-end engineering and permits; the environmental and social impact assessment is planned, with terms of reference to be submitted to MINEPDED in 2027 and a certificate of environmental compliance targeted for late 2028. Phase 1 works are planned from the first quarter of 2029, with first heat targeted for the second half of 2030 and ramp-up in 2031. The capacities, jobs and schedules shown on this site are targets or indicative values, clearly labelled as such.
Source: Cameroon Tribune, « Kribi : le Premier ministre, chef du gouvernement est là », 30 Dec 2024