From mineral resource to industrial value

Labs · Project timeline

What is verified, what is planned, and when?

9 verified, dated facts since the 2023 Mining Code, each with its source, and 3 statements reported by the press or claimed by the party concerned, labelled as such. After 10 October 2026 everything is planned, an objective or indicative: these steps may move.

Inputs

Show
Actor

Result

Derived

—

Verified, sourced facts

—

Reported statements, not verified

—

Planned, objective or indicative steps

10 Oct 2026

Latest verified fact

Showing 22 milestones: 9 verified facts with their sources, 3 statements reported by a single press source or claimed by the party concerned, and 10 planned, objective or indicative steps, which may move with permits, engineering, the market and financing.

Cameroon Steel projectContext: State, port, industrial zone

  1. 19 Dec 2023

    VerifiedContext

    The Mining Code sets local transformation

    Law No. 2023/014 provides that at least 15% of mine output be destined for local transformation (art. 40(4)).

    Source: Loi n° 2023/014 du 19 décembre 2023 portant Code minier

  2. 30 Dec 2024

    VerifiedProject

    Foundation stone laid at Mboro

    The Prime Minister, Head of Government, representing the Head of State, lays the foundation stone of the Kribi steel complex, with a target capacity of 1 Mt/yr.

    Source: Cameroon Tribune, 30 Dec 2024 and 2 Jan 2025

  3. 6 Aug 2025

    VerifiedContext

    Kribi 225 kV line launched

    A 42 km line from the gas power plant to the port and a 225/30 kV substation: 100 MW at first, then 330 to 400 MW.

    Source: Port Autonome de Kribi, « Kribi franchit la ligne électrique 225 kV », 6 Aug 2025

  4. 10 Dec 2025

    VerifiedContext

    A committee for mines–metallurgy integration

    The Prime Minister sets up a committee tasked, among other things, with securing ore supply for local steelmakers and enforcing local transformation.

    Source: EcoMatin, 16 Apr 2026

  5. 12 Dec 2025

    ReportedProject

    Mbalam and the 15% local transformation

    The convention of Cameroon Mining Company, the sister company holding the Mbalam exploitation permit, is reported to provide for 15% of its output to be transformed locally; the same report presents Cameroon Steel as the future national steel hub of the programme.

    Source: Camer.be via AllAfrica, 12 Dec 2025

  6. 26 Feb 2026

    VerifiedContext

    KPIZ S.A. is launched, with a steel cluster

    The company that will develop the Kribi industrial-port zone (about 4,000 ha) lists “steelmaking linked to mineral exports” among its clusters.

    Source: Investir au Cameroun, 4 Mar 2026

  7. 7–9 Apr 2026

    ReportedProject

    The complex is reported on the port’s inspection tour

    According to one press report, the tour by the Director General of the Port Autonome de Kribi includes, for the mining sector, the “modern steel complex of Kribi”.

    Source: Bougna.net, 8 Apr 2026

  8. 4 Jun 2026

    VerifiedContext

    Memorandum for the Édéa–Kribi–Lolabé–Campo railway

    The Government and partners sign a memorandum on the studies, financing, construction and operation of a line of about 185 km.

    Source: Port Autonome de Kribi, communiqué, 4 Jun 2026

  9. 19 Aug 2026

    VerifiedContext

    Minister visits the 225/30 kV substation

    The Minister of Water and Energy inspects the line, the substation and the port’s water plant, whose production is announced for early 2027.

    Source: Port Autonome de Kribi, « Énergie et infrastructures : un nouvel élan… », 19 Aug 2026

  10. 10 Oct 2026

    VerifiedProject

    Ten white papers published

    Cameroon Steel publishes ten sourced studies on market, technology, energy, climate, skills and quality.

    Source: Cameroon Steel

  11. End 2026

    PlannedContext

    Announced commissioning of the 225 kV line

    Date announced by the Port Autonome de Kribi for the line and substation that will supply the industrial zone.

    Source: Port Autonome de Kribi, communiqués of 6 Aug 2025 and 19 Aug 2026 (site visit by the Minister of Water and Energy)

  12. Early 2027

    PlannedContext

    Announced start of the port’s water plant

    A dedicated intake and treatment plant for the port platform: production is announced for early 2027.

    Source: Port Autonome de Kribi, « Énergie et infrastructures : un nouvel élan pour la compétitivité du Port de Kribi », 19 Aug 2026

  13. First half 2027

    ObjectiveProject

    Site surveys and environmental scoping

    Topographic and geotechnical surveys; terms of reference of the environmental and social impact assessment submitted to the Ministry of Environment.

    Source: Cameroon Steel, reference configuration RC-1 (edition 10 Oct 2026)

  14. 2027

    ObjectiveProject

    Front-end engineering for Phase 1

    Engineering with the technology supplier; power and water supply agreements.

    Source: Cameroon Steel, reference configuration RC-1 (edition 10 Oct 2026)

  15. 2027–2028

    ObjectiveProject

    Two-season impact study and public hearings

    Field measurements in the dry and rainy seasons, public consultations, then the certificate of environmental compliance, targeted for the fourth quarter of 2028.

    Source: Cameroon Steel, reference configuration RC-1 (edition 10 Oct 2026)

  16. Late 2028 to Q1 2029

    ObjectiveProject

    Financing, then start of Phase 1 works after the environmental certificate

    Financial close then, once the certificate of environmental compliance is granted, start of construction of the Phase 1 electric melt shop and mills from the first quarter of 2029.

    Source: Cameroon Steel, reference configuration RC-1 (edition 10 Oct 2026)

  17. H2 2030

    ObjectiveProject

    Phase 1: first heat

    Hot commissioning and first heat, then ramp-up in 2031 towards the nameplate capacity of 0.3 Mt/yr of reinforcing bar and wire rod.

    Source: Cameroon Steel, reference configuration RC-1 (edition 10 Oct 2026)

  18. 2032–2034

    IndicativeProject

    Phase 2: sections, to 0.5 Mt/yr

    Angles, channels and flats from a second melt line and a sections mill, subject to market and financing.

    Source: Cameroon Steel, reference configuration RC-1 (edition 10 Oct 2026)

  19. After 2034

    IndicativeProject

    Phase 3: heavy sections, to 1 Mt/yr

    H- and I-beams and heavy sections, with the melt-shop expansion, subject to market and financing.

    Source: Cameroon Steel, reference configuration RC-1 (edition 10 Oct 2026)

  20. Later

    IndicativeProject

    Option: direct reduction of Cameroonian ore

    A direct-reduction module could process national ore, subject to its quality, gas supply and approvals.

    Source: Cameroon Steel, reference configuration RC-1 (edition 10 Oct 2026)

In the timeline, ← → move between milestones, ↑ ↓ switch lanes.

Statuses and rules

StatusMeaningStatusSource
VerifiedDated public fact, with its sourceVerifiedNational press, official communiqués, legal texts
ReportedDated statement resting on a single press source, or a claim by the party concerned: reported, not verifiedReportedPress articles cited at each milestone
PlannedDate announced by a third party (port, ministry)PlannedPort Autonome de Kribi communiqués, cited by title and date
ObjectiveStep of Cameroon Steel’s RC-1 reference schedule, which may moveObjectiveCameroon Steel, RC-1 reference schedule
IndicativeLong-term option, subject to market and financingIndicativeCameroon Steel, RC-1 reference schedule
Rules checked automaticallyNo verified or reported fact dated after 10 Oct 2026; no planned step dated before 2026; every milestone has a sourceCheckAutomated site test, run at every release

How this is calculated

Sources. Every verified fact links to its source: national press, Port Autonome de Kribi communiqués (cited by title and date), official texts. This timeline reuses the one on the Company and project page, with three port milestones added. Phases follow the RC-1 reference schedule: Phase 2 from 2032 to 2034, Phase 3 after 2034.

Statuses. Verified: a dated public fact. Reported: a dated statement that rests on a single press source, or a claim made by the party concerned; we cite it without treating it as verified. Planned: a date announced by a third party (port, ministry). Objective: a step of Cameroon Steel’s RC-1 reference schedule. Indicative: later phases and the long-term option. Objectives depend on permits, engineering, the market and financing; they can move.

Reading. Above the axis, project steps; below it, the context (State, port, industrial zone). The orange line marks the edition of 10 October 2026: to its left, facts; to its right, intentions.