White paper 02 · Annex A

Method, assumptions and calculations

This annex explains how the evidence in the paper was gathered and graded, how derived figures were calculated, and which planning assumptions were used, with their ranges. The data behind every chart are published with the web edition of the paper as JSON files, one per chart, with their sources and status.

Reading
8 min
Length
1,911 words
Edition of
10 October 2026
In this chapter (6)
  1. A.1 Evidence and status codes
  2. A.2 Planning assumptions for one steel tenant
  3. A.3 Derived calculations
  4. A.4 Maps and distances
  5. A.5 Scenario in Figure 10.2
  6. A.6 Limitations

A.1 Evidence and status codes

The research for this paper used public sources available on or before 10 October 2026: legal texts, regulators’ reports, statements and documents of the Port Autonome de Kribi (PAK) and of Kribi Port Industrial Zone S.A. (KPIZ), statistics from Cameroon’s national statistics institute (INS) and from UN Comtrade, reports of international organisations, peer-reviewed studies and reputable business press. Documents of PAK are cited by title and date, without web links.

Every figure and table carries one of four status codes:

  • Sourced: the number was read in the cited source.
  • Derived: the number is Cameroon Steel’s arithmetic on sourced inputs; the calculation is shown below.
  • Assumed: the number is a stated planning assumption, with a range.
  • Illustrative: the exhibit shows a scenario or a schematic, not a measurement or a forecast.

Where sources conflict, the paper says so in the text and states which figure it uses, preferring primary over secondary sources and the most recent edition of a dataset. Cameroon Steel’s own planning figures, drawn from the Cameroon Steel reference configuration RC-1 (planning estimate) for a 1 Mtpa electric-arc-furnace long-products works, are cited as [S112] and described as indicative; they are not design values and do not represent commitments. The phased pathway of that configuration is described in White paper 03, Chapter 9.

A.2 Planning assumptions for one steel tenant

Table A.1 assumedIndicative planning assumptions for one electric-arc-furnace long-products works, with ranges

Parameter Central value Range Status Basis
Capacity, first phase 0.3 Mtpa finished product (nameplate) Expected sustained output 270,000 to 300,000 t a year Assumed Cameroon Steel planning [S112]
Capacity, first and second phases 0.5 Mtpa 0.45 to 0.5 Assumed [S112]
Capacity, full 1.0 Mtpa 0.85 to 1.0 Assumed Public record of design capacity [S40]; [S112]
EAF electricity 450 kWh per tonne of liquid steel; about 490 kWh/t with 30% DRI or HBI (upper planning value) 347 to 500 Sourced IFC EHS Guidelines, 2007 [S75]; [S112]
Rolling electricity 110 kWh per tonne of product 70 to 140 Sourced [S75]
Auxiliaries (ladle furnace, caster, oxygen, utilities) 70 kWh per tonne of liquid steel 50 to 100 Assumed [S112]
Induction billet heating, first-phase line 300 kWh per tonne of billet, applied to the tonnage rolled 150 to 400 Assumed [S112]
Operating basis for average load 8,000 hours a year n/a Assumed [S112]
Metallic yield 0.88 t liquid per t metallics 0.85 to 0.91 Assumed [S112]
Casting and rolling yield 0.94 t product per t liquid 0.92 to 0.96 Assumed [S112]
Share of DRI or HBI in the charge 30% 20 to 50 Assumed [S112]
Domestic scrap available to one tenant 30,000 t a year 0 to 60,000 Assumed Bounded by the national estimate of 53,000 to 62,000 t a year, 2006 [S168]; [S112]
Water make-up, closed loop 2.0 m³ per tonne of product 1.5 to 3.0 Assumed worldsteel 2024 averages [S77]; [S112]
Oxygen 35 Nm³ per tonne of liquid steel 25 to 45 Assumed [S112]
EAF slag 140 kg per tonne of liquid steel 110 to 180 Derived IFC gives 110 to 180 kg of solid waste per tonne for EAF steelmaking [S75], taken here as mostly slag
EAF dust 15 kg per tonne of liquid steel 10 to 20 Assumed Planning range [S112]; the European reference document reports 10 to 30 kg [S76]
Mill scale 20 kg per tonne of product 15 to 25 Assumed [S112]
Maximum electrical demand, first phase 55 MVA 45 to 65 Assumed [S112]
Maximum electrical demand, full 160 MVA 130 to 190 Assumed [S112]
Truck payload; working days 30 t; 300 days a year n/a Assumed [S112]
Consumables (lime, alloys, electrodes, refractories) 6% of finished output n/a Assumed [S112]
Phase 1 schedule Works from the first quarter of 2029; first heat in the second half of 2030; ramp-up in 2031 n/a Assumed [S112]
Grid carbon intensity 226 g CO₂ per kWh 200 to 300 Sourced Ember via Our World in Data, 2024 [S78]; kept as a conservative planning value
Exchange rates 655.957 FCFA per euro (fixed); 600 FCFA per US dollar (planning) 560 to 650 FCFA per US dollar Assumed Fixed parity; planning rate

Source: as listed.

With these assumptions the indicative annual balances are: at 0.3 Mtpa, about 289 GWh of electricity (36 MW average), 0.6 million m³ of make-up water, about 45 kt of slag and about 351 kt of port-linked inbound cargo; at 0.5 Mtpa, about 422 GWh (53 MW), 1.0 million m³ and about 604 kt; at 1.0 Mtpa, about 753 GWh (94 MW), 2.0 million m³, about 149 kt of slag, 16 kt of dust, 37 million Nm³ of oxygen and about 1.24 Mt of port-linked inbound cargo [S112]. Port-linked inbound cargo is the metallic charge less domestic scrap, plus consumables. The electricity of the first phase is 0.319 Mt of liquid steel (0.3 Mt ÷ 0.94) × 520 kWh/t + 0.3 Mt rolled × 410 kWh/t = 289 GWh; ÷ 8,000 h = 36 MW. The induction heating applies to the first-phase line only, so each further tonne of product adds about 663 kWh (520 ÷ 0.94 + 110). At the upper planning value of 490 kWh/t for the furnace, the first phase’s average load would be about 1.5 MW higher.

A.3 Derived calculations

Table A.2 derivedDerived figures used in the paper and how they were calculated

Figure in the paper Calculation Result
Average value of chapter 72 imports, 2025 170,094 million FCFA ÷ 412,049 t; ÷ 655.957 FCFA per euro 413 FCFA/kg; about €630/t
Total material moved at 1 Mtpa (Figure 1.1) Imported scrap 816 kt + domestic scrap 30 kt + DRI 363 kt + consumables (6% of finished output) 60 kt + products 1,000 kt + slag 149 kt + scale 20 kt + dust 16 kt About 2.45 Mt
Port-linked inbound cargo Metallic charge minus domestic scrap plus consumables: 1,209 minus 30 plus 60 kt at 1 Mtpa; 363 minus 30 plus 18 kt for a first phase About 1.24 Mt and 351 kt
Truck-km by distance (Figure 1.2) (Port-linked inbound + 0.5 × outbound) ÷ 30 t × 2 × distance 11.6 million truck-km at 1 Mtpa and 100 km
Truck movements if all flows went by road (Figure 6.3) (Metallic charge + finished output) ÷ 30 t ÷ 300 days 74, 123 and 245 a day at 0.3, 0.5 and 1 Mtpa
Of which inside the port domain Imported metallics (metallic charge minus domestic scrap) ÷ 30 t ÷ 300 days 37, 64 and 131 a day
Of which on the public road (Finished output + domestic scrap) ÷ 30 t ÷ 300 days 37, 59 and 114 a day; 20, 31 and 59 if half the output ships by sea
Train equivalents of public-road flows Public-road loads × 30 t ÷ 1,500 t 0.7, 1.2 and 2.3 trains a day
Melting cost of a 10 FCFA/kWh tariff difference 450 to 490 kWh/t × 10 FCFA/kWh About 4,500 to 4,900 FCFA per tonne of liquid steel
Capacity margin, 2025 2,033 MW installed minus 1,278 MW peak 755 MW
Kribi gas plant capacity factor, 2025 559.67 GWh ÷ (216 MW × 8,760 h) About 30%
Average legacy high-voltage price, 2025 17.80 bn FCFA ÷ 969.03 GWh 18.4 FCFA/kWh
All-in price, 9 to 10 MW band, 2026 Demand charge 15,500 FCFA/kW/month and energy 9 FCFA/kWh (2023 base), each escalated by 10% a year in 2024, 2025 and 2026; 650 hours a month About 43.7 FCFA/kWh
Transmission charge (16.18 million FCFA/MW/year × 100 MW) ÷ (100 MW × 8,760 h × 0.8) + 0.41 FCFA/kWh About 2.7 FCFA/kWh
KPIZ plan per hectare €795 million ÷ 4,000 ha About €199,000/ha
Servicing cost per hectare at Mboro 3.5 bn FCFA ÷ 20 ha About 175 million FCFA/ha
Ratio of land requested to land allocated 3,883 ha ÷ 196 ha About 20
Lobé minimum flow as annual volume 3.5 m³/s × 31.5 million s About 110 million m³
Town equivalent of 8.5 million m³ a year 8.5 million m³ ÷ (0.15 m³ per person per day × 365) About 155,000 people
Rainwater harvest (Chapter 5) Area × 10,000 m²/ha × 2.836 m × run-off coefficient 0.8 0.11, 0.23 and 0.45 million m³ for 5, 10 and 20 ha
Gas for 1 Mtpa of DRI 1 Mt × 10 GJ/t; about 1.09 PJ per billion cubic feet About 10 PJ, about 9 bcf

Source: inputs as cited in the chapters; arithmetic by Cameroon Steel.

A.4 Maps and distances

The Kribi map (Figure 2.1) was drawn from an OpenStreetMap extract downloaded through the Overpass API with a data base of 24 July 2026, projected to UTM zone 32N. It shows coastline, roads, rivers, residential and industrial land use, protected-area limits and named places as mapped by OpenStreetMap contributors [S111]. The 225 kV line is drawn as a straight schematic between the gas power plant and the port, and the substation position is indicative. The regional map (Figure 6.2) uses Natural Earth admin-0 boundaries [S110]; corridors are schematic lines through the cities they serve, and the Mbalam-Nabeba deposits are placed approximately. No project boundary or parcel is shown on any map.

Straight-line distances (Figures 6.1 and 9.2) are geodesic distances on the WGS84 ellipsoid. City distances are measured between approximate city-centre positions; distances to protected areas are measured from the centroid of the port breakwater as mapped in OpenStreetMap to the nearest vertex of each protected-area boundary. Road distances are longer.

A.5 Scenario in Figure 10.2

The zone-load scenario is illustrative. Steel and metals load follows one tenant’s phases on the schedule of Cameroon Steel’s reference configuration [S112]. It is zero until the first heat of Phase 1 in the second half of 2030, averages about 10 MW in 2030 and reaches 36 MW in 2031. Phase 2 (second melt line and light/medium sections mill), indicatively 2032 to 2034, is drawn as a ramp from the start of 2032, giving annual averages of about 40 MW in 2032 and 53 MW in 2034. Phase 3 (melt-shop expansion and heavy-section mill), after 2034, takes the tenant to about 94 MW in 2037. A second metals tenant from the mid-2030s brings steel and metals load to about 120 MW in 2037 and 160 MW in 2040. Other tenants’ load rises from 10 MW in 2026 to 150 MW in 2040. Total load reaches the first stage’s 100 MW in 2032. Supply follows the announced stages: about 13 MW locally available before 2027, 100 MW from 2027 and the midpoint of 330 to 400 MW from 2031. No date has been published for that second stage: 2031 is assumed in this paper and is the date it recommends. The purpose is to show the timing problem, not to forecast demand.

A.6 Limitations

The paper is a desk study. It does not include site measurements, interviews with the authorities or confidential information, and it does not assess any individual project’s economics. Statistics from operators and the press were used where official series are not available, and conflicts are reported. Readers should treat the indicative figures as orders of magnitude for planning.

Sources cited in this chapter

Bracketed markers refer to these sources; the full list is in the annex. Full list of sources

  1. S112Cameroon Steel reference configuration RC-1 (planning estimate), edition 10 October 2026. Cameroon Steel, 10 October 2026.Cited by title and date
  2. S40Industrialisation: la voie royale de l’émergence. Cameroon Tribune, 2 January 2025.cameroon-tribune.cm/article.html/68558/fr.html/details_2
  3. S75Environmental, Health, and Safety Guidelines for Integrated Steel Mills. IFC, World Bank Group, 30 April 2007.ifc.org/content/dam/ifc/doc/2000/2007-integrated-steel-mills-ehs-guide…
  4. S168La récupération et le recyclage des déchets ferromagnétiques: analyse de la situation au Cameroun (Déchets, Revue francophone d’écologie industrielle n°48). Bidoung J., Fomethe A., Yantio G., Melo U. (ENSP Yaoundé / MIPROMALO), 2007.eid.episciences.org/7942/pdf
  5. S77Sustainability Indicators 2025 report. worldsteel, November 2025 (updated February 2026).worldsteel.org/wider-sustainability/sustainability-indicators/
  6. S76Best Available Techniques Reference Document for Iron and Steel Production (EUR 25521). European Commission, Joint Research Centre, 2013.bureau-industrial-transformation.jrc.ec.europa.eu/sites/default/files/…
  7. S78Carbon intensity of electricity generation (Ember data). Our World in Data.ourworldindata.org/grapher/carbon-intensity-electricity
  8. S111OpenStreetMap extract for the Kribi area (Overpass API, data base 24 July 2026), © OpenStreetMap contributors, ODbL. OpenStreetMap Foundation, 24 July 2026.openstreetmap.org/copyright
  9. S110Natural Earth 1:50m Cultural Vectors, Admin 0 countries (version 5). Natural Earth.naturalearthdata.com/

Cite this chapter

Cameroon Steel (2026). Kribi can become Central Africa’s steel platform if infrastructure keeps pace. White paper 02, annex A: Method, assumptions and calculations. CS-WP-02. https://www.cameroon-steel.com/en/library/kribi-steel-platform/annex-method/