White paper 02 · Chapter 11
Next studies: twelve facts to establish, most of them within a year
This paper relies on public sources available on 10 October 2026. Some facts that matter for a steel platform at Kribi are still to be published, are reported inconsistently, or are still to be measured. This chapter lists them as next studies, explains why each matters, and proposes how and by whom each could be carried out. None of the studies affects the paper’s central finding, that Kribi has the hard attributes of a steel platform and needs its enabling infrastructure to arrive in sequence. Several of them, however, determine how fast and how large that platform can become.
In this chapter (3)
11.1 How the next studies were identified
Each chapter’s evidence was graded as it was assembled. A fact was treated as established when it came from a primary source, such as a decree, a regulator’s report or an official statement, or from two independent reputable sources that agree. It was treated as reported when only one secondary source was available, and as to be studied when no public source was found or when sources conflict without a way to reconcile them. Figures that are Cameroon Steel’s own planning assumptions are marked as indicative throughout and are not counted among the next studies; they are explained in Annex A.
11.2 The studies that matter most
Power system data. The short-circuit level that the new 225/30 kV substation at the port will offer at its busbars is to be published, together with the rules for connecting large fluctuating loads. These numbers decide how large an arc furnace can be connected without compensation, and how much compensation each tenant must install (Chapter 4). The timing and financing of the second stage of the 225 kV system, from about 100 MW to 330 to 400 MW, are also to be published by the public authorities [S25].
Gas availability. How much gas from the fields offshore Kribi can be committed to industry for twenty years after the departure of the Hilli floating liquefaction vessel in July 2026 is the subject of a reserve study: the reserves are to be publicly certified, and the larger Yoyo-Yolanda resource awaits a final investment decision [S67][S68][S69]. This is decisive for any direct-reduction module and for captive or extended gas-fired generation.
Water plant capacity. The capacity of the port-platform water plant due in early 2027, and the share reserved for industry, are to be published by PAK and KPIZ [S26].
Bulk berth design. The technical design, phasing and user-allocation rules of the mineral terminal agreed in a memorandum of understanding on 4 November 2025 will be set as its structuring advances; the dated public statement is that completion is expected within five to six years of March 2026 [S32][S33][S03].
Land framework and tariffs. KPIZ’s new contractual framework for tenants, the entity that will sign new agreements, standard terms for heavy industry, and whether the 2018 tariff book, including its commercial levy of 3% of turnover, will continue to apply are to be published [S10][S11][S114].
Environmental baseline. Measured air-quality, noise and receiving-water data for the zone are to be collected; the background fine-particle figure used in this paper is modelled [S92]. A strategic environmental assessment of the zone is the matching study at zone level.
Hazardous-waste capacity. A licensed hazardous-waste facility or zinc-recovery route for the region is to be identified and contracted (Chapter 5).
Road and rail timetables. The completion date of the Édéa-Kribi road reconstruction is to be published [S27], and the June 2026 railway agreement is to be followed by a timetable for studies, financing and construction [S41].
Table 11.1 derivedNext studies, their purpose and how to carry them out
| # | Study | Why it matters | Method | Who | When |
|---|---|---|---|---|---|
| 1 | Short-circuit levels at the port substation; connection rules for fluctuating loads | Sets maximum furnace size and compensation needs | Grid study by SONATREL; publication in a zone power-quality code | SONATREL, KPIZ, ARSEL | Before commissioning, end 2026 |
| 2 | Timing and financing of the second 225 kV stage (330 to 400 MW) | Sets the date from which the cluster can take a second heavy tenant | Financing plan and procurement schedule | MINEE, PAK, lenders | 2027 |
| 3 | Long-term industrial gas availability after July 2026 | Decides direct reduction and captive generation | Independent reserve audit; gas allocation policy | SNH, MINEE | 2027 |
| 4 | Capacity of the port-platform water plant and industrial share | Sizes plant water systems and tariffs | Publication by PAK and KPIZ | PAK, KPIZ | Early 2027 |
| 5 | Mineral-terminal design and berth allocation | Determines the berth for steel imports | Publication of design basis; user-allocation rules | Terminal consortium, PAK | 2027 |
| 6 | KPIZ contractual framework and tariffs for heavy industry | Sets the terms on which long-lived plants are built | Publication of template agreements and tariff schedule | KPIZ | 2027 |
| 7 | Consistent port traffic series by cargo type | Bulk planning; benchmark credibility | Annual statistics by terminal and cargo | PAK | Next annual report |
| 8 | Measured environmental baseline for the zone | Permits and lender diligence | Zone monitoring network; strategic environmental assessment | KPIZ, MINEPDED | Start 2027 |
| 9 | Hazardous-waste route | Licence condition for an arc furnace | Feasibility of shared secure cell and export route | KPIZ, licensed operators | Before first heat |
| 10 | Édéa-Kribi road completion date | Outbound logistics and road safety | Publication of works programme | MINTP | 2027 |
| 11 | Railway timetable | Cluster-scale logistics | Feasibility study and financing plan | Government, promoters | 2027 to 2028 |
| 12 | Independent verification of benchmark zone statistics | Calibration of targets | Use of audited or third-party data where available | Researchers | Ongoing |
Source: Cameroon Steel assessment.
11.3 How Cameroon Steel will update this paper
This is a first edition. Cameroon Steel intends to update it when material new facts become public, in particular the commissioning of the 225 kV substation, the publication of KPIZ’s contractual framework, and decisions on the mineral terminal and the railway. Corrections and additional sources are welcome and will be acknowledged in later editions.
Sources cited in this chapter
Bracketed markers refer to these sources; the full list is in the annex. Full list of sources
- S25Kribi franchit la ligne électrique 225 kV. Port Autonome de Kribi, 6 August 2025.Cited by title and date
- S67Données pétrolières 2025. Société Nationale des Hydrocarbures (SNH), June 2026.snh.cm/wp-content/uploads/2026/06/Donnees-petrolieres-2025.pdf
- S68Cameroon FLNG Terminal. Global Energy Monitor (GEM.wiki; tertiary), October 2026.gem.wiki/Cameroon_FLNG_Terminal
- S69Cameroon’s SNH eyes Yoyo-Yolanda and new exploration blocks to sustain gas growth. Business in Cameroon, 6 July 2026.businessincameroon.com/energy/0607-16422-cameroon-s-snh-eyes-yoyo-yola…
- S26Énergie et infrastructures: un nouvel élan pour la compétitivité du Port de Kribi. Port Autonome de Kribi, 19 August 2026.Cited by title and date
- S32Port de Kribi: un terminal minéralier d’avenir. Port Autonome de Kribi, 4 November 2025.Cited by title and date
- S33Kribi Deep Sea Port, investors partner to construct 125-million-tonne mineral terminal worth $2 billion. Business in Cameroon, 5 November 2025.businessincameroon.com/transport/0511-15300-kribi-deep-sea-port-invest…
- S03Zone industrialo-portuaire de Kribi (KPIZ): jusqu’à +8 points de croissance et 150 000 emplois attendus sur 15 ans. Investir au Cameroun, 4 March 2026.investiraucameroun.com/gestion-publique/0403-23163-zone-industrialo-po…
- S10Gestion de la zone industrielle du Port de Kribi: une nouvelle organisation mise en place. Cameroon Tribune, 28 May 2026.cameroon-tribune.cm/article.html/77128/fr.html/details_2
- S11Kribi Port unveils new management framework for industrial-zone transition. Business in Cameroon, 1 June 2026.businessincameroon.com/public-management/0106-16249-kribi-port-unveils…
- S114Recueil général des tarifs applicables aux prestations rendues par le Port Autonome de Kribi (homologated by the APN, 2018). Port Autonome de Kribi / Autorité Portuaire Nationale, 2018.Cited by title and date
- S92Copernicus Atmosphere Monitoring Service global reanalysis, PM2.5 for the grid cell nearest the Port of Kribi, 2024 to 2025 (via the Open-Meteo air-quality API). ECMWF Copernicus / Open-Meteo.air-quality-api.open-meteo.com/v1/air-quality
- S27Bilan et perspectives: les voyants sont au vert. Port Autonome de Kribi, 13 March 2025.Cited by title and date
- S41Ligne ferroviaire Édéa-Kribi-Lolabé-Campo: une nouvelle étape pour la connectivité du Port de Kribi. Port Autonome de Kribi, 4 June 2026.Cited by title and date
Cite this chapter
Cameroon Steel (2026). Kribi can become Central Africa’s steel platform if infrastructure keeps pace. White paper 02, chapter 11: Next studies: twelve facts to establish, most of them within a year. CS-WP-02. https://www.cameroon-steel.com/en/library/kribi-steel-platform/evidence-gaps/
Source