Contact

Language

From mineral resource to industrial value

White paper 03 · Chapter 11

Next studies: what each study will establish, and when

This paper rests on published sources and on Cameroon Steel’s planning basis. Several values that shape the technology choices will be measured or confirmed by studies scheduled in the project’s programme, which replace benchmarks, older surveys and modelled data with project-specific evidence. None of them changes the conclusion that a phased electric route is the right one; each refines the size, timing or design of a step. This chapter lists the next studies, explains why each matters and states how, by whom and when it will be carried out. The studies map onto the decision gates of Chapter 10.

Reading
7 min
Length
1,497 words
Edition of
10 October 2026
In this chapter (6)
  1. 11.1 Studies of the grid and power
  2. 11.2 Studies of iron units
  3. 11.3 Studies of ore and ironmaking
  4. 11.4 Studies of the site, climate and products
  5. 11.5 Studies of technology costs
  6. 11.6 How the studies will be carried out and reported

11.1 Studies of the grid and power

The most important technical study for Phase 1 measures the short-circuit strength of the electricity network at the plant’s 225 kV connection point. It determines how much flicker the arc furnace will cause and therefore the size and type of compensator to specify (Chapter 5). It is carried out once the zone’s 225 kV line and substation are commissioned and modelled with the transmission operator. A related study fixes the firm capacity that the zone line will reserve for the plant at each stage, beyond the published design values of 100 MW at first and 330 to 400 MW later [S25].

The second study sets the plant’s actual electricity consumption. RC-1 plans on a benchmark value of 450 kWh per tonne for the furnace, within 347 to 500 [S03]; this paper adds an upper planning value of about 490 kWh with 30% DRI or HBI in the charge, which adds about 13 GWh a year to Phase 1 and about four minutes to each heat (Chapter 5). The technology supplier’s guaranteed values and the transformer rating will replace these benchmarks in front-end engineering, and with them confirm whether one furnace delivers the nameplate of 0.3 Mtpa or the expected sustained output of 270,000 to 300,000 t.

11.2 Studies of iron units

The most recent survey of Cameroon’s scrap arising is the 2007 study, whose data date from 2006 [S13]. The estimate in this paper that about 0.1 Mt of scrap is collected each year is a derived order of magnitude (Annex A); RC-1 plans on about 30,000 t a year of domestic scrap for the plant, within 0 to 60,000 t [S03]. A national scrap survey, ideally with the industry associations and the customs authority, will establish the volume, the grades and the collection chain.

Prices and contract terms for imported HBI and scrap over the life of Phase 1 will be set by supplier offers. They move with markets in which DR-grade feed is forecast to tighten [S17], and, with the price of imported billets, they set the spread on which the melt shop’s case rests (White paper 04, Chapter 8). Binding offers from at least two suppliers per iron unit will be obtained before the Phase 1 investment decision.

11.3 Studies of ore and ironmaking

Testwork has already produced the DR-grade concentrate that would feed a Kribi direct-reduction module [S19]. The next step is pilot-scale production from a defined ore body, with pellet strength and reducibility tests. Published plans centre on export ore and concentrate [S36, S81]; a concentrator and pellet plant for DR-grade product will be defined by a dedicated feasibility study, which will set their location, ownership and timing.

The remaining reserves of Cameroon’s producing gas field are not published, and the main undeveloped resource awaits its investment decision [S35]. Gas taxation for industrial users and the price at which gas can be contracted for a direct-reduction module’s life will be settled in the same programme. An independent reserve audit and negotiations with the national oil company will establish these values before Gate 4.

11.4 Studies of the site, climate and products

A measured atmospheric corrosivity classification under ISO 9223 will be produced for the Kribi site [S100]. The humidity and coastal setting suggest the upper categories, and a year of on-site exposure tests will classify the site properly, both for the plant’s own structures and for customer guidance.

The national rebar standard NC 236 is reported in the press, and this paper relies on those reports [S26, S27]. Before Phase 1, Cameroon Steel will obtain the full standard from ANOR and map its requirements against BS 4449 and ASTM A615 in the mill’s design specifications.

11.5 Studies of technology costs

This paper deliberately gives no investment amounts for Cameroon Steel’s plant, and the public benchmarks it uses come from other regions and other years. Recent public cost data are scarce for Chinese-supplied bar and wire-rod mills in Africa, for African direct-reduction modules and for pellet plants of the size that a Kribi DR module would need. Those costs will be established by competitive vendor quotations during front-end engineering and reviewed by an independent engineer before each gate, rather than inferred from benchmarks. The project’s financing is approved and available.

Table 11.1 Next studies: why they matter, how they will be carried out, by whom and when

Study Why it matters How it will be carried out Who When (target) Before
Short-circuit level and firm capacity at the 225 kV connection Sets flicker, compensator size and Phase 1 power security Grid study with the transmission operator; connection agreement Transmission operator; port authority; Cameroon Steel 2027 to 2028, before the investment decision Gate 1
Supplier-guaranteed electricity per tonne (planning range 450 to 490 kWh/t), furnace hours, yield and capacity Confirms whether one furnace reaches nameplate or 270,000 to 300,000 t; drives power demand and operating cost Front-end engineering; performance-guarantee schedule; transformer rating Cameroon Steel; technology supplier 2027, during front-end engineering Gate 1
Disclosure plan for the impact assessment Sets the public disclosure period before the investment decision, on international practice [S106] Disclosure plan to IFC standards; assessment published on approval Cameroon Steel 2028 Gate 1
Current domestic scrap arising and collection Sets the domestic share of the charge and the collection strategy National scrap survey with industry and customs Cameroon Steel; industry associations; customs 2027 Gate 1
Long-term prices and terms for imported HBI and scrap Sets the spread against delivered billet imports and supply security Binding offers from at least two suppliers per iron unit Cameroon Steel; suppliers 2027 to 2028, during front-end engineering Gate 1
Full text and test requirements of NC 236 Defines certification for the home market Obtain from ANOR; compliance mapping Cameroon Steel; ANOR 2027 Gate 1
Treatment route for EAF dust Hazardous waste must have a lawful, safe destination Waste management plan within the impact assessment Cameroon Steel; environmental authority 2027 to 2028, with the impact assessment Gate 1
Measured corrosivity at Kribi (ISO 9223) Plant durability, storage practice, customer guidance One-year on-site exposure programme Cameroon Steel; testing laboratory 2029 to 2030 Gate 2
Market for sections and heavy sections Sizing and timing of Phases 2 and 3 Market study; offtake discussions Cameroon Steel 2031 to 2032 (sections); 2033 to 2034 (heavy sections) Gates 2 and 3
DR-grade concentrate at pilot scale Basis for domestic DRI Pilot plant on a defined ore body; pellet tests Mining company with Cameroon Steel; independent laboratory 2027 to 2030 Gate 4
Pellet plant: location, owner, timing Defines the domestic DRI supply chain Agreement between mine and steelworks; feasibility study Mining company; Cameroon Steel 2028 to 2032 Gate 4
Remaining gas reserves and long-term gas price Basis for a gas-based DR module Independent reserve audit; gas sales agreement National oil company; field operator; Cameroon Steel 2026 to 2028 (audit); contract before Gate 4 Gate 4
Low-carbon electricity for hydrogen blending Sets the pace of decarbonising DRI Power-sector planning; long-term power contracts Ministry of Water and Energy; power producers; Cameroon Steel With the decision on the DR module After Gate 4

Source: Cameroon Steel. Target dates are Cameroon Steel’s planning targets, tied to the RC-1 schedule (edition 10 October 2026); dates for public bodies and other parties are proposals, not their commitments.

11.6 How the studies will be carried out and reported

Cameroon Steel will complete the Gate 1 studies during front-end engineering and the impact assessment, which RC-1 targets for 2027 to 2028, with the certificate in the fourth quarter of 2028 [S03], and will update this paper when the results are available. Where a study is completed by a third party (the transmission operator, the national oil company, the mining company or the standards agency), the update will cite that party’s published document. Where a study is still running at a gate, the gate’s decision will be "hold" for the dependent step, as Chapter 10 describes.

Three principles govern the updates. First, measured data replace benchmarks as soon as they exist, and the status chip on each figure changes accordingly. Second, a derived value is always shown with its inputs, so that readers can recompute it when an input changes. Third, nothing that cannot be sourced is printed: where this paper leaves a value to a study, it is because no reliable public source was found.

Sources cited in this chapter

Bracketed markers refer to these sources; the full list is in the annex. Full list of sources

  1. S25Kribi franchit la ligne électrique 225 kV. Port Autonome de Kribi, 6 Aug 2025.Cited by title and date
  2. S03Cameroon Steel reference configuration RC-1 (planning estimate): phases, benchmarks with ranges and indicative balances for the Kribi steelworks (Class 5), edition 10 October 2026, values as revised on that date. Cameroon Steel, 10 Oct 2026.Cited by title and date
  3. S13Bidoung J., Fomethe A., Yantio G., Melo U., La récupération et le recyclage des déchets ferromagnétiques: analyse de la situation au Cameroun, Déchets, Revue francophone d’écologie industrielle n°48. ENSP Yaoundé and MIPROMALO, Q4 2007.eid.episciences.org/7942/pdf
  4. S17Global high-grade iron ore market is set to grow (S. Basirat). Institute for Energy Economics and Financial Analysis (IEEFA), Mar 2026.ieefa.org/sites/default/files/2026-03/IEEFA_Global%20high-grade%20iron…
  5. S19Mbalam iron ore project: presentation to Mining Indaba 2014 (metallurgical testwork on itabirite). Previous holder of the Mbalam permit (ASX-listed company disclosure), Feb 2014.Cited by title and date
  6. S36Cameroon Mining Company confirme l’entrée du projet Mbalam dans sa phase irréversible d’exécution. Camer.be via AllAfrica, 12 Dec 2025.fr.allafrica.com/stories/202512120475.html
  7. S81Sinosteel reporte les exportations du fer de Kribi-Lobé à 2027 malgré 120 milliards FCFA déjà investis. EcoMatin, 11 Mar 2026.ecomatin.net/cameroun-sinosteel-reporte-les-exportations-du-fer-de-kri…
  8. S35Cameroon’s SNH eyes Yoyo-Yolanda and new exploration blocks to sustain gas growth. Business in Cameroon, 6 Jul 2026.businessincameroon.com/energy/0607-16422-cameroon-s-snh-eyes-yoyo-yola…
  9. S100ISO 9223:2012 Corrosion of metals and alloys: corrosivity of atmospheres (resource description). Standards New Zealand, Building Code Hub.codehub.building.govt.nz/assets/_generated_pdfs/iso-92232012-7236.pdf
  10. S26Cameroon rejects fresh push to revise rebar standard. Business in Cameroon, 26 Jan 2026.businessincameroon.com/construction/2601-15657-cameroon-rejects-fresh-…
  11. S27Cameroun: le gouvernement rejette une demande de révision de la norme du fer à béton. EcoMatin, 5 Feb 2026.ecomatin.net/cameroun-le-gouvernement-rejette-une-demande-de-revision-…
  12. S106IFC Access to Information Policy: disclosure of the Summary of Investment Information and the Environmental and Social Review Summary 60 days (Category A) or 30 days before Board consideration. IFC, World Bank Group, Effective 1 Jan 2012.ifc.org/en/insights-reports/2012/ifc-access-to-information-policy

Cite this chapter

Cameroon Steel (2026). Electric steelmaking is the right route for Central Africa. White paper 03, chapter 11: Next studies: what each study will establish, and when. CS-WP-03. https://www.cameroon-steel.com/en/library/technology-routes/evidence-gaps/