Contact

Language

From mineral resource to industrial value

Labs · Power demand

How much electricity does an electric steelworks need, hour by hour?

For Phase 1, about 289 GWh a year: 36.1 MW on average over 8,000 hours, a load that swings between about 16 and 51 MW, and a 15-minute average peak near 47 MW.

Inputs

t/yr
Working pattern
h/yr

RC-1: 8,000 hours a year.

min

About one heat an hour for a furnace of the 40 t class.

kWh/t

IFC benchmark: 347 to 500 kWh per tonne of liquid steel.

Billet reheating

Result

Derived

To make 300,000 t of products a year, the steelworks would use about 289 GWh of electricity: 36.1 MW on average over 8,000 operating hours. The load would swing between about 16 and 51 MW from minute to minute, with a 15-minute average peak near 47 MW: 47% of the 100 MW initially planned at the Kribi substation. The energy is 3.6% of Cameroon’s 2025 electricity generation, about 90% of it hydro.

289GWh

Electricity per year

36.1MW

Average load over operating hours

47MW

Peak, 15-minute average (billing basis)

16–51MW

Load range, one-minute values

25MW

Arc furnace: mean active power with the arc on, order of magnitude

47%

Of the initial 100 MW at the Kribi substation (15-minute peak)

3.6%

Of national generation in 2025

A typical day

The load curve, minute by minute

025507510000:0003:0006:0009:0012:0015:0018:0021:0024:00Kribi substation, initial capacity: 100 MWAverage 36.1 MW15-minute peak 47 MWMW
Stacked profile: auxiliaries, mill and reheating, ladle furnace, arc furnace. The orange steps follow each heat: bore-in, melting, recharge with power off, bore-in, melting, refining, then tapping and turnaround with power off. An illustrative day, the same as in White paper 05 (Figure 9.2), drawn as two-minute averages; an arc furnace also fluctuates within seconds, which the model does not show. The pale line marks the 15-minute average peak. Derived, indicative result.

Where the electricity goes

Arc furnace144 GWh · 50%Ladle furnace12 GWh · 4%Mill and reheating123 GWh · 43%Auxiliaries10 GWh · 4%

The peak against the supply

Kribi, initial 100 MW47%Kribi, 330 to 400 MW later13%National peak, 1,278 MW (2025)3.7%
Average load hour by hour (MW)
000102030405060708091011121314151617181920212223
36.236.936.236.336.935.735.736.636.136.436.735.836.535.835.836.136.435.336.035.936.436.136.534.7

Model assumptions

20 assumptions
ParameterValue usedRangeStatusSource
Annual output (Phase 1)300,000 t/yr of finished products50,000 – 1,000,000AssumptionCameroon Steel reference configuration RC-1 (edition 10 Oct 2026): 0.3 Mt/yr first phase, a planning assumption; 1 Mt/yr target design capacity (Cameroon Tribune, 2 Jan 2025)
Electric arc furnace450 kWh/t liquid steel347 – 500SourcedIFC EHS Guidelines for Integrated Steel Mills (2007): 1,250–1,800 MJ/t = 347–500 kWh/t; RC-1 uses 450
Ladle furnace (refining)37.5 kWh/t liquid steel30.0 – 50.0AssumptionGeneric benchmark 30–50 kWh/t; with auxiliaries it makes the 70 kWh/t of RC-1
Auxiliaries (caster, oxygen, water, compressed air, lighting)32.5 kWh/t liquid steel20.0 – 50.0DerivedCameroon Steel reference configuration RC-1, edition 10 Oct 2026 (planning estimate, not a design figure): 70 kWh/t including the ladle furnace
Rolling110 kWh/t product70 – 150SourcedIFC EHS Guidelines (2007): rolling 70–140 kWh/t; generic range up to 150 kWh/t
Induction billet reheating300 kWh/t product150 – 400AssumptionCameroon Steel reference configuration RC-1, edition 10 Oct 2026 (planning estimate, not a design figure): electric induction heating, partly hot-charged (150–400 kWh/t)
Alternative: gas-fired reheating furnace1.3 GJ/t product1.1 – 1.6AssumptionCameroon Steel reference configuration RC-1, edition 10 Oct 2026 (planning estimate, not a design figure): walking-beam furnace (1.1–1.6 GJ/t); electricity not counted
Casting and rolling yield0.94 t/t0.92 – 0.96AssumptionCameroon Steel reference configuration RC-1, edition 10 Oct 2026 (planning estimate, not a design figure): 0.92–0.96
Operating hours per year8,000 h/yr6,000 – 8,400AssumptionCameroon Steel reference configuration RC-1, edition 10 Oct 2026 (planning estimate, not a design figure): 8,000 operating hours a year
Tap-to-tap time60 min40 – 70AssumptionGeneric modern electric arc furnace practice: 40–70 minutes; about one heat an hour in the illustrative day of White paper 05
Furnace of the 40 t class: heats of about 40 t of liquid steel40 t—AssumptionCameroon Steel reference configuration RC-1, edition 10 Oct 2026 (planning estimate, not a design figure): one arc furnace of the 40 t class in Phase 1
Power-on share of the cycle0.73 share0.70 – 0.82AssumptionWhite paper 05, Annex A: recharge, tapping and turnaround take about 27% of the cycle; generic practice 20–30%
Ladle-furnace heating share0.33 share0.25 – 0.60AssumptionWhite paper 05, Annex A: a ladle-furnace pulse of about 20 minutes in each cycle (illustrative)
Auxiliary load outside production hours0.40 share0.20 – 0.60IllustrativeIllustrative: water, compressed air and lighting keep running at reduced load
Kribi 225 kV line and substation, initial capacity100 MW—SourcedPort Autonome de Kribi, communiqués of 6 Aug 2025 and 19 Aug 2026
Later capacity (330 to 400 MW, central value)365 MW330 – 400SourcedPort Autonome de Kribi, communiqués of 6 Aug 2025 and 19 Aug 2026
Cameroon electricity generation (2025)8,119.9 GWh—SourcedARSEL, Rapport d’activités 2025 (7 Sep 2026): 8,119.9 GWh, of which 7,272.4 GWh hydro
National peak demand (2025)1,278 MW—SourcedARSEL, Rapport d’activités 2025 (7 Sep 2026): 1,278 MW peak for 2,033 MW installed
Hydropower share of generation (2025)90%—SourcedARSEL, Rapport d’activités 2025 (7 Sep 2026)
Grid carbon intensity (2024)226 g CO₂/kWh200 – 300SourcedEmber via Our World in Data: Cameroon 225.9 g CO₂e/kWh in 2024, when hydropower supplied about 72% of generation; ARSEL reports about 90% hydro for 2025; the 2024 factor is kept as the prudent value

How this is calculated

Annual energy = liquid steel × (arc furnace + ladle furnace + auxiliaries) + products × (rolling + electric reheating), with liquid steel = products ÷ 0.94. With the default values (450 + 70 kWh/t of liquid steel, 37.5 of it for the ladle furnace; 110 + 300 kWh/t of product) the model returns the 289 GWh a year of the RC-1 reference configuration for Phase 1 and, over 8,000 operating hours, its average load of 36.1 MW.

The typical day is the one in White paper 05 (Chapter 9, Figure 9.2; method in Annex A). The arc furnace repeats its tap-to-tap cycle: bore-in, melting, recharge, bore-in, melting, refining, then tapping and turnaround, with power off for about 27% of the time. Its power varies around each step (standard deviation of 35% during bore-in, 14% during melting and 4% during refining, on a fixed pseudo-random sequence) and is capped at about 110% of the melting level. Heats follow one another after a short random delay; the ladle furnace gives one pulse per cycle; the mill, reheating and auxiliaries run steadily. Each component is then scaled so that its daily energy is exact.

Which peak? The tool quotes the 15-minute average peak, the basis on which maximum demand is billed: about 47 MW at the default values, as in the white paper. The range shown (about 16 to 51 MW) runs from the 5th to the 99th percentile of the one-minute values during operating hours. The planned maximum demand of Phase 1 is 55 MVA (45 to 65).

Two shifts. With two shifts the plant runs 16 hours on each operating day, so the hours entered (8,000 by default) become about 5,300 actual operating hours. The same annual energy is packed into them: the average over operating hours rises to about 54 MW, against 36.1 MW over the 8,000-hour basis, and the peak rises. Outside those hours only the idling auxiliaries draw power (less than 1 MW at night).

Feasibility. In Phase 1 a single furnace of the 40 t class melts all the steel: about one heat of about 40 t an hour. If the output, tap-to-tap time and operating hours entered would need much heavier heats, the tool says so: the result then describes several melting lines, not a one-furnace plant.

Limits. Generic benchmarks, not equipment ratings: the furnace power is given as an order of magnitude (about 25 MW of active power with the arc on, at the default values). No second-by-second fluctuation (flicker), no planned stoppages. The peak sizes the connection and compensation; annual energy sizes the contract. The hydro share assumes the plant receives the national mix.