Labs · Power demand
How much electricity does an electric steelworks need, hour by hour?
For Phase 1, about 289 GWh a year: 36.1 MW on average over 8,000 hours, a load that swings between about 16 and 51 MW, and a 15-minute average peak near 47 MW.
Result
DerivedTo make 300,000 t of products a year, the steelworks would use about 289 GWh of electricity: 36.1 MW on average over 8,000 operating hours. The load would swing between about 16 and 51 MW from minute to minute, with a 15-minute average peak near 47 MW: 47% of the 100 MW initially planned at the Kribi substation. The energy is 3.6% of Cameroon’s 2025 electricity generation, about 90% of it hydro.
289GWh
Electricity per year
36.1MW
Average load over operating hours
47MW
Peak, 15-minute average (billing basis)
16–51MW
Load range, one-minute values
25MW
Arc furnace: mean active power with the arc on, order of magnitude
47%
Of the initial 100 MW at the Kribi substation (15-minute peak)
3.6%
Of national generation in 2025
A typical day
The load curve, minute by minute
Where the electricity goes
The peak against the supply
| 00 | 01 | 02 | 03 | 04 | 05 | 06 | 07 | 08 | 09 | 10 | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18 | 19 | 20 | 21 | 22 | 23 |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 36.2 | 36.9 | 36.2 | 36.3 | 36.9 | 35.7 | 35.7 | 36.6 | 36.1 | 36.4 | 36.7 | 35.8 | 36.5 | 35.8 | 35.8 | 36.1 | 36.4 | 35.3 | 36.0 | 35.9 | 36.4 | 36.1 | 36.5 | 34.7 |
Model assumptions
20 assumptions
| Parameter | Value used | Range | Status | Source |
|---|---|---|---|---|
| Annual output (Phase 1) | 300,000 t/yr of finished products | 50,000 – 1,000,000 | Assumption | Cameroon Steel reference configuration RC-1 (edition 10 Oct 2026): 0.3 Mt/yr first phase, a planning assumption; 1 Mt/yr target design capacity (Cameroon Tribune, 2 Jan 2025) |
| Electric arc furnace | 450 kWh/t liquid steel | 347 – 500 | Sourced | IFC EHS Guidelines for Integrated Steel Mills (2007): 1,250–1,800 MJ/t = 347–500 kWh/t; RC-1 uses 450 |
| Ladle furnace (refining) | 37.5 kWh/t liquid steel | 30.0 – 50.0 | Assumption | Generic benchmark 30–50 kWh/t; with auxiliaries it makes the 70 kWh/t of RC-1 |
| Auxiliaries (caster, oxygen, water, compressed air, lighting) | 32.5 kWh/t liquid steel | 20.0 – 50.0 | Derived | Cameroon Steel reference configuration RC-1, edition 10 Oct 2026 (planning estimate, not a design figure): 70 kWh/t including the ladle furnace |
| Rolling | 110 kWh/t product | 70 – 150 | Sourced | IFC EHS Guidelines (2007): rolling 70–140 kWh/t; generic range up to 150 kWh/t |
| Induction billet reheating | 300 kWh/t product | 150 – 400 | Assumption | Cameroon Steel reference configuration RC-1, edition 10 Oct 2026 (planning estimate, not a design figure): electric induction heating, partly hot-charged (150–400 kWh/t) |
| Alternative: gas-fired reheating furnace | 1.3 GJ/t product | 1.1 – 1.6 | Assumption | Cameroon Steel reference configuration RC-1, edition 10 Oct 2026 (planning estimate, not a design figure): walking-beam furnace (1.1–1.6 GJ/t); electricity not counted |
| Casting and rolling yield | 0.94 t/t | 0.92 – 0.96 | Assumption | Cameroon Steel reference configuration RC-1, edition 10 Oct 2026 (planning estimate, not a design figure): 0.92–0.96 |
| Operating hours per year | 8,000 h/yr | 6,000 – 8,400 | Assumption | Cameroon Steel reference configuration RC-1, edition 10 Oct 2026 (planning estimate, not a design figure): 8,000 operating hours a year |
| Tap-to-tap time | 60 min | 40 – 70 | Assumption | Generic modern electric arc furnace practice: 40–70 minutes; about one heat an hour in the illustrative day of White paper 05 |
| Furnace of the 40 t class: heats of about 40 t of liquid steel | 40 t | — | Assumption | Cameroon Steel reference configuration RC-1, edition 10 Oct 2026 (planning estimate, not a design figure): one arc furnace of the 40 t class in Phase 1 |
| Power-on share of the cycle | 0.73 share | 0.70 – 0.82 | Assumption | White paper 05, Annex A: recharge, tapping and turnaround take about 27% of the cycle; generic practice 20–30% |
| Ladle-furnace heating share | 0.33 share | 0.25 – 0.60 | Assumption | White paper 05, Annex A: a ladle-furnace pulse of about 20 minutes in each cycle (illustrative) |
| Auxiliary load outside production hours | 0.40 share | 0.20 – 0.60 | Illustrative | Illustrative: water, compressed air and lighting keep running at reduced load |
| Kribi 225 kV line and substation, initial capacity | 100 MW | — | Sourced | Port Autonome de Kribi, communiqués of 6 Aug 2025 and 19 Aug 2026 |
| Later capacity (330 to 400 MW, central value) | 365 MW | 330 – 400 | Sourced | Port Autonome de Kribi, communiqués of 6 Aug 2025 and 19 Aug 2026 |
| Cameroon electricity generation (2025) | 8,119.9 GWh | — | Sourced | ARSEL, Rapport d’activités 2025 (7 Sep 2026): 8,119.9 GWh, of which 7,272.4 GWh hydro |
| National peak demand (2025) | 1,278 MW | — | Sourced | ARSEL, Rapport d’activités 2025 (7 Sep 2026): 1,278 MW peak for 2,033 MW installed |
| Hydropower share of generation (2025) | 90% | — | Sourced | ARSEL, Rapport d’activités 2025 (7 Sep 2026) |
| Grid carbon intensity (2024) | 226 g CO₂/kWh | 200 – 300 | Sourced | Ember via Our World in Data: Cameroon 225.9 g CO₂e/kWh in 2024, when hydropower supplied about 72% of generation; ARSEL reports about 90% hydro for 2025; the 2024 factor is kept as the prudent value |
How this is calculated
Annual energy = liquid steel × (arc furnace + ladle furnace + auxiliaries) + products × (rolling + electric reheating), with liquid steel = products ÷ 0.94. With the default values (450 + 70 kWh/t of liquid steel, 37.5 of it for the ladle furnace; 110 + 300 kWh/t of product) the model returns the 289 GWh a year of the RC-1 reference configuration for Phase 1 and, over 8,000 operating hours, its average load of 36.1 MW.
The typical day is the one in White paper 05 (Chapter 9, Figure 9.2; method in Annex A). The arc furnace repeats its tap-to-tap cycle: bore-in, melting, recharge, bore-in, melting, refining, then tapping and turnaround, with power off for about 27% of the time. Its power varies around each step (standard deviation of 35% during bore-in, 14% during melting and 4% during refining, on a fixed pseudo-random sequence) and is capped at about 110% of the melting level. Heats follow one another after a short random delay; the ladle furnace gives one pulse per cycle; the mill, reheating and auxiliaries run steadily. Each component is then scaled so that its daily energy is exact.
Which peak? The tool quotes the 15-minute average peak, the basis on which maximum demand is billed: about 47 MW at the default values, as in the white paper. The range shown (about 16 to 51 MW) runs from the 5th to the 99th percentile of the one-minute values during operating hours. The planned maximum demand of Phase 1 is 55 MVA (45 to 65).
Two shifts. With two shifts the plant runs 16 hours on each operating day, so the hours entered (8,000 by default) become about 5,300 actual operating hours. The same annual energy is packed into them: the average over operating hours rises to about 54 MW, against 36.1 MW over the 8,000-hour basis, and the peak rises. Outside those hours only the idling auxiliaries draw power (less than 1 MW at night).
Feasibility. In Phase 1 a single furnace of the 40 t class melts all the steel: about one heat of about 40 t an hour. If the output, tap-to-tap time and operating hours entered would need much heavier heats, the tool says so: the result then describes several melting lines, not a one-furnace plant.
Limits. Generic benchmarks, not equipment ratings: the furnace power is given as an order of magnitude (about 25 MW of active power with the arc on, at the default values). No second-by-second fluctuation (flicker), no planned stoppages. The peak sizes the connection and compensation; annual energy sizes the contract. The hydro share assumes the plant receives the national mix.
Sources
- IFC, EHS Guidelines for Integrated Steel Mills (2007): arc furnace 347–500 kWh/t, rolling 70–140 kWh/t
- Cameroon Steel, RC-1 reference configuration (10 Oct 2026): 289 GWh/yr and an average of 36.1 MW over 8,000 hours in Phase 1; White paper 05, Chapter 9 and Annex A, for the typical day
- Port Autonome de Kribi, communiqués of 6 Aug 2025 and 19 Aug 2026: 225 kV line, 100 MW then 330 to 400 MW
- ARSEL, 2025 activity report: generation 8,119.9 GWh, peak 1,278 MW, about 90% hydro
- Ember via Our World in Data: 225.9 g CO₂e/kWh in 2024, when hydropower supplied about 72% of generation